53
1. Turn off power to the compressor, crank case
heater and module.*
2. Isolate the compressor and evacuate per accept-
ed industry practice.
3. Inside the Rear Terminal Box (figure 5.6)
a. Remove terminal lug nuts holding voltage
sensing eyelets.
b. Loosen terminal lug connections.
c. Remove T-box anchor screw holding the box
to the compressor.
Figure 5.6 Terminal Box
4. Unplug the low and high voltage Harness
Connectors (Deutsch plugs) from the terminal
box. (figure 5.7) *
Figure 5.7 Deutsch Plugs
5. Remove screw “B” from the side box into the rear
terminal box.
6. Unplug all harness connections in the side box,
and loosen temperature sensor ground screw. *
7. Remove the front cover (2 screws) and unplug the
communication plug from the module and careful-
ly extract the communication line out of the mod-
ule. *
Low
Voltage
High
Voltage
Voltage Sensing Leads
(4x) anchor screws - same
location as conventional 2D/3D
5.2 Compressor Replacement - 2D and 3D
5.2.1 Removal of the Compressor
Note: The following instructions assume the same front module is being used on the new compressor. If the
module is being replaced, refer to module change-out procedures for start-up procedures. Steps with an *
indicate they pertain to module replacement instructions in section 5.3.
Reference Drawing of 2D / 3D Enclosure and Accessories
TEMPERATURE SENSOR
GROUND SCREW
LOW PRESSURE CUTOUT SWITCH AND CONNECTOR
White Dot in Center
Blue Wire Harness (LPCO)
HOUSING COVER NUTS
SCREWS “A”
FRONT CONTROL BOX
HARNESS ANCHOR
HIGH PRESSURE CUTOUT SWITCH AND CONNECTOR
Red Dot in Center
Red Wire Harness (HPCO)
DISCHARGE TEMPERATURE PROBE
Black/White Harness
Attach Green Wire to Ground Screw
SCREW “B”
SIDE BOX
DEMAND COOLING
SOLENOID COIL
Brown Wire Harness
(Liquid Injection)
HARNESS CONNECTORS
To Remove: Depress 2 tabs before pulling
To Install: Push in until connector “snaps”
Install Torque
25-30 ft-lb