13
Figure 3.4 Controller Setup Screen
3. Verify that the number of ISD devices listed on the
Controller Setup Screen matches the number of
devices connected to the E2.
At this point you must choose how you want the ISD
devices to be displayed in the E2. To avoid confusion,
it is recommended that the devices be displayed in
the same order that they are located on the rack. This
involves commissioning each device individually. To
follow this procedure, continue with step 4 below:
4. For this process to work properly the E2 must
communicate with one ISD device at a time. To
begin, turn ON only the first ISD device on the
rack. Be sure to allow enough time for the ISD to
perform its self diagnostics before proceeding
(approximately 30 seconds).
5. Use the arrow key to highlight the first ISD device
listed on the controller setup screen. Press F4:
Set Address to bring up the node recovery screen.
Enter 1 for the number of nodes to be recov-
ered.
After communications have been established with a
module, the E2 screen will update and list the device
as Node Found. Following the node recovery
process, the Controller Setup Screen should look like
figure 3.5. Note: You must refresh the screen by back-
ing out and returning for the compressor serial num-
ber to be displayed.
Figure 3.5 Controller Setup Screen (Following Node
Recovery)
6. Once the first ISD device has been successfully
commissioned, turn it OFF.
7. Continue the process by turning ON only the
second ISD device on the rack. Use the arrow key
to highlight the second ISD device listed on the
controller setup screen. Press F4: Set Address to
bring up the node recovery screen. Enter 1 for the
number of nodes to be recovered.
8. Continue this process by turning OFF the second
device and turning ON the third…repeat until all
ISD devices have been commissioned. It is impor-
tant that only one device be powered at a time and
that 1 is entered for the number of nodes to be
recovered.
3.2 Suction Group Setup
In order for the E2 to control compressor operation
the proper input and output values must be entered
into the system. This is accomplished by creating a
suction group application in the rack controller.
Programming of the suction group will depend upon
the system as well as the options desired by the end
user. The following section covers the steps neces-
sary to setup the sample rack shown in figure 3.9.
From the Main Menu:
1. Press 6 (Add / Delete Application).
2. Press 1 (Add Application).
3. Press F4 (Lookup) and select Suction Group from
the option list.
4. Enter the number of suction groups controlled by
this E2.
5. When prompted by the E2 to edit the application,
Press Y for yes.