Instruction Manual
D101299X012
RSS Valve
September 2014
4
1. The control valve assembly should be installed in a horizontal pipeline with the v alve stem in a vertical position.
Before installing in any other orientation, consult your Emerson Process Management sales office.
Flowthroughthevalvemustbeinthedirectionindicatedbythearrowcastonthevalve(figure7).
2. With a leak-off bonnet construction, remove the pipe plug (key 20, not shown) and install the leak-off piping into
thetappinginthebonnet(key2,figure10).
3. If continuous operation is required during inspection or maintenance, install a three-way bypass around the control
valve assembly.
4. For a valve used with a fail-closed actuator, remove the shim (key 24, not shown) from between the bonnet and the
travel stop. Discard the shim.
5. If the actuator and valve are shipped separately, refer to the appropriate actuator instruction manual for the
actuator mounting procedure.
Note
Bench sets for Fish er 657 and 667 actuators must be adjusted after installation on the RSS valve. The heavy duty bellows on the
RSSvalvehasasignificantspringratethatmustbe included in the bench set for proper operation.
Figure 2. Typical Line Flange Gasket (Key 17)
PTFE
COMPOSITION
STAINLESS STEEL
SECTION A-A
10B3224-C
A5039
A
A