Install replaceable filter dryer
assembly in liquid supply line G
** To first cooling module
or bypass flow controller
Dimensions are
approximate and
subject to change
without notice.
G - Supply to Cooling Units
F - Return From Cooling Units
B - Liquid
Refrigerant Lines
* Allow 8" (204mm) of clearance for filter replacement
** To ensure all refrigerant flow is filtered, install the filter dryer assembly
between the discharge line of the XDC and the first bypass flow controller
or the first cooling module.
*** Use double discharge risers in DX hot gas lines that are 15 feet (4.6m) in height.
This will allow proper oil return to the compressors when the system is running
at low loads. Refer to the Liebert XDC user manual SL-16671 for further information.
*** A - Hot Gas
Refrigerant Lines
* Orientation determined
by installer.
23"
(584.2mm)
6" (152mm)
47"
(1193.8mm)
44"
(1117.6mm)
DPN000768